Start-Up Procedure

  1. Make sure that the jumper at JP1 (Enable control) pins 1 and 2 are covered to shunt EN to GND, disabling the output.
  2. Apply appropriate input voltage to VIN (J1-2) and GND (J1-1).
  3. Move the jumper at JP1 (Enable control) pin 2 and 1 (EN and GND) to enable the output.