SNOU182 February   2021 TLV3605

 

  1.   Trademarks
  2. 1Introduction
  3. 2Features
  4. 3EVM Specifications
  5. 4Recommended Equipment
  6. 5How to Make a Propagation Delay Measurement With Latch
  7. 6Board Setup
    1. 6.1 Supply Voltage
    2. 6.2 Inputs
    3. 6.3 Outputs
  8. 7Layout Guidelines
  9. 8Schematic
  10. 9Bill of Materials

Recommended Equipment

  • Power Supply
  • High Speed Functional Generator with dual outputs
    • Fast rise/fall time recommended (≤ 500ps)
  • High Speed Oscilloscope with 50Ω terminations
    • Differential probes with built in 100Ω terminations can be used to terminate the output properly
  • SMA Cables/adapters
    • All forced input voltages and signals must have matched cable lengths.
      • IN+, IN-, SHUTDOWN, LE/HYST
    • All sensed voltages and signals
      • LE/HYST SENSE, IN+SENSE, IN-SENSE, SHUTDOWN SENSE, OUT+, and OUT-