SLAU823 October   2019 TMUXHS4212

 

  1.   TMUXHS4212 Evaluation Module User's Guide
    1.     Trademarks
    2. 1 Introduction
    3. 2 Setup and Configuration
      1. 2.1 Signal Connection
      2. 2.2 AC Coupling Capacitors
      3. 2.3 Jumper Configuration
      4. 2.4 Power
      5. 2.5 Calibration
      6. 2.6 REACH Compliance
    4. 3 Schematics
    5. 4 Bill of Materials
      1. 4.1 TMUXHS4212EVM BOM

Signal Connection

The EVM provides SMP receptacles for the high-speed signal connections. Each SMP receptacle is labeled with the signal's port (A, B, or C), channel (0 or 1), and polarity (P or N). SMA to SMP cables may be required to connect to test equipment or fixtures. The signal traces are all equal length and have 50 Ω single-ended impedance.