SLUA888 May   2018 TPS53622 , TPS53659 , TPS53679 , TPS53681

 

  1.   NVM Programming for VR13 Power Controllers
    1.     Trademarks
    2. 1 Introduction
      1. 1.1 Software Tools
        1. 1.1.1 Fusion Digital Power Designer
        2. 1.1.2 Fusion Manufacturing Tool
        3. 1.1.3 Online and Offline Modes
        4. 1.1.4 Relevant File Formats
      2. 1.2 Hardware Tools
        1. 1.2.1 USB-to-GPIO Dongle
    3. 2 Technical Overview
      1. 2.1 Hardware Connections
      2. 2.2 Communication Protocol and Interfacing
      3. 2.3 Programming Process
        1. 2.3.1 Programming Procedure
        2. 2.3.2 Example NVM Data
    4. 3 Use of TI Programming Tools
      1. 3.1 Fusion Digital Power Designer
        1. 3.1.1 Build and Export a System (.tifsp) File
        2. 3.1.2 View a Project File or System File Offline
        3. 3.1.3 Import a Project File to a Single Online Device
        4. 3.1.4 Import a System File to an Online System
        5. 3.1.5 Export CSV Script for Third Party Tools
        6. 3.1.6 Compare Two Project Files
        7. 3.1.7 Build a System File from Existing Project Files
      2. 3.2 Fusion Manufacturing Tool
        1. 3.2.1 Import a System File
      3. 3.3 TI Programming Board
        1. 3.3.1 Board and Connector Description
        2. 3.3.2 Placing devices in the 40-pin socket

Import a Project File to a Single Online Device

  1. Connect the USB-GPIO to a board.
  2. Apply 3.3 V to the V3P3 pin of the controller device.
  3. Start the Fusion Digital Power Designer software.
  4. From the System View window, Click to configure device
  5. From the File menu, select Import to device
  6. Select Project File
  7. Click Next.
  8. 12_import_proj.gifFigure 19. Import to Devcie
    13_import_proj2.gifFigure 20. Import Project File
    14_import_proj3.gifFigure 21. Select Project File
  9. Click Select All to import all parameters of the device.
  10. Click Write Checked.
  11. 15_import_proj4.gifFigure 22. Select All and Write Checked Parameters
    16_import_proj5.gifFigure 23. Successful Project File Import
  12. When the Project file import finishes, the software does not automatically issue an NVM store operation command. You must click Store Config to NVM to update NVM settings after you import a Project file.
  13. 17_import_proj6.gifFigure 24. Store to NVM