SLUUC27C June   2019  – July 2022 BQ25611D , BQ25619

 

  1.   BQ25611D, BQ25619 (BMS025) Evaluation Module
  2.   Trademarks
  3. 1Introduction
    1. 1.1 EVM Features
    2. 1.2 I/O Descriptions
  4. 2Test Summary
    1. 2.1 Equipment
    2. 2.2 Equipment Setup
    3. 2.3 Software Setup
    4. 2.4 Test Procedure
      1. 2.4.1 Initial Settings
      2. 2.4.2 Communication Verification
      3. 2.4.3 Charger Mode Verification
      4. 2.4.4 Boost Mode Verification
      5. 2.4.5 Evaluation Results
      6. 2.4.6 Helpful Tips
  5. 3PCB Layout Guideline
  6. 4Board Layout, Schematic, and Bill of Materials
    1. 4.1 Board Layout
    2. 4.2 Schematics
    3. 4.3 Bill of Materials
  7. 5Revision History

Charger Mode Verification

Use the following steps for charger mode verification:

  1. PS1 should be on from Section 2.4.1. In the EVM software, click GUID-A2D5000D-CD07-46F6-A2BF-9D87705B91D7-low.gif twice.
    • Verify that all Fault statuses read "Normal"
      GUID-A11B7AC2-30C7-4044-8C5D-B5B9CED63F30-low.png
    • Verify → STAT LED (D5) is ON
  2. Enable Load #1 (see Section 2.2) and take measurements as follows:
    • Measure → VSYS (SYS-TP17 and PGND-TP30) = 3.65V ±0.3V
    • Measure → VBAT (BATTERY-TP16 and PGND-TP30) = 2.5V ±0.2V
    • Measure → IBAT = 240mA ±50mA
  3. Change Load #1 to 3.7V and take measurements as follows:
    • Measure → VSYS (SYS-TP17 and PGND-TP30) = 3.8V ±0.3V
    • Measure → VBAT (BATTERY-TP16 and PGND-TP30) = 3.7V ±0.2V
    • Measure → IBAT = 480mA ±200mA
  4. In the EVM software, set
    • Measure → IIN = 500mA ±200mA