Definitions

This procedure details how to configure the BMS051 evaluation board. For the test procedure, the following naming conventions are followed. Refer to the BMS051 schematic for details.

VXXX:External voltage supply name (VADP, VBT, VSBT).
LOADW:External load name (LOADR, LOADI).
V(TPyyy):Voltage at internal test point TPyyy. For example, V(TP12) means the voltage at TP12.
V(Jxx):Voltage at jack terminal Jxx.
V(TP(XXX)):Voltage at test point “XXX”. For example, V(ACDET) means the voltage at the test point which is marked as “ACDET”.
V(XXX, YYY):Voltage across point XXX and YYY.
I(JXX(YYY)):Current going out from the YYY terminal of jack XX.
Jxx(BBB):Terminal or pin BBB of jack xx.
Jxx ON :Internal jumper Jxx terminals are shorted.
Jxx OFF:Internal jumper Jxx terminals are open.
Jxx (-YY-) ON:Internal jumper Jxx adjacent terminals marked as “YY” are shorted.
Measure: → A,BCheck specified parameters A, B. If measured values are not within specified limits, the unit under test has failed.
Observe → A,BObserve if A, B occurs. If they do not occur, the unit under test has failed.

Assembly drawings have locations for jumpers, test points, and individual components.