Use the following guidelines to set up and test
the equipment:
- Set power supply #1 for 40VDC, 6A current limit
and then turn off the supply.
- Connect the output of power supply #1 in series with a current meter to J1 (VIN and PGND).
- Connect a voltage meter across J1 (VIN) and J1 (PGND).
- Connect load #1 in series with a current meter to J3 (VBAT and PGND).
- Connect a voltage meter across J5 (VBAT and PGND).
- Set 23.5V at electronic load input.
- Connect J5 to the EV2400. Connect J5 to the I2C PORT 2 on the EV2400.
- Make sure the jumpers are installed as indicated in IO and Jumper Descriptions.
- Unplug Jumper 13.
- Turn on the computer and power supply #1. Open the bqStudio software.
- Select Charger and click the Next button.
- Select Charger_1_00_BQ25756.bqz on the Select a Target Page.
- After selecting the target device, click Field View and then click the Read Register button.
- Set WATCHDOG and EN_CHG to disabled.
- In 16 Bit Registers, set ICHG_REG to
4000mA and IPRECHG to 1000mA.
- Set EN_CHG to enabled. Plug in Jumper 13.
- Set power supply #1 to 40V, measure
V(J1(VAC)) = 40V ± 0.5V
I(J1(IAC)) = 2.4A ± 0.5A
V(J3(VBAT)) =
23.5V ± 0.5V I(J3(IBAT)) = 3.9A ±
0.5A
- Set power supply #1 for 23V, measure
V(J1(VAC)) = 23V ± 0.5V
I(J1(IAC)) = 4.1A ± 0.5A
V(J3(VBAT)) =
23.5V ± 0.5V I(J3(IBAT)) = 3.9A ±
0.5A
- Set power supply #1 for 19V, measure
V(J1(VAC)) = 19V ± 0.5V
I(J1(IAC)) = 5A ± 0.5A
V(J3(VBAT)) =
23.5V ± 0.5V I(J3(IBAT)) = 3.9A ±
0.5A