SLUUCV1 November   2023

 

  1.   1
  2.   Description
  3.   Get Started
  4.   Features
  5.   Applications
  6.   6
  7. 1Evaluation Module Overview
    1. 1.1 Introduction
    2. 1.2 Kit Contents
    3. 1.3 Specification
    4. 1.4 Device Information
  8. 2Hardware
    1. 2.1 Setup
      1. 2.1.1 Connector Descriptions
      2. 2.1.2 Hardware Setup
  9. 3Implementation Results
    1. 3.1 Input and Output Capacitors
      1. 3.1.1 Feedforward Capacitor
  10. 4Hardware Design Files
    1. 4.1 Schematic
    2. 4.2 PCB Layouts
    3. 4.3 Bill of Materials
  11. 5Additional Information
    1.     Trademarks

Hardware Setup

To operate the EVM, set jumpers JP1 to the desired positions per Section 2.1.1. Connect the input supply to J1, and connect the load to J2.