SNLA474A October   2024  – October 2024 DS90UB971-Q1

 

  1.   1
  2.   Abstract
  3.   Trademarks
  4. Introduction
  5. Typical Test Standards Overview
    1. 2.1 ISO 10605 Standard
    2. 2.2 Performance Status Categorization
  6. FPD-Link Hardware Optimizations
    1. 3.1 Connector Grounding
    2. 3.2 PCB to Enclosure Grounding
    3. 3.3 MODE Selection
  7. FPD-Link Software Optimizations
    1. 4.1 LOCK Detection Tuning
    2. 4.2 Parity Error Handling
    3. 4.3 Forward Error Correction
      1. 4.3.1 FEC Test Capabilities
  8. Optimization Test Data
    1. 5.1 Baseline Hardware - No Software Optimization
    2. 5.2 Optimized Hardware - No Software Optimization
    3. 5.3 Optimized Hardware and Software
  9. Example Scripts for Software Optimization
  10. Additional System Level Software Options
  11. Summary
  12. References
  13. 10Revision History

Performance Status Categorization

System level ESD performance is classified during testing at each test level using a lettering system. The OEM typically defines requirements for system performance status at the various levels.

Table 2-1 Performance Status Table
Status Description
A No performance deviation

(typically means no perceivable interruption of video for camera systems)

B Temporary disruption, automatic recovery

(typically means momentary visual glitch which is perceivable)

C Performance disruption which does not automatically recover

(typically means a black screen is encountered where power cycle or re-initialization of the system is required to recover video)

D Permanent damage to the DUT