Start-Up Sequence

Start-up behavior is shown in the following figure for no load. Channel 2 is the input voltage and Channel 1 is the output voltage.

GUID-20231206-SS0I-DNK7-QQCK-L4H50HMFSFNK-low.png Figure 3-2 Start-Up