SLUUC73A March   2020  – December 2023 BQ25616

 

  1.   1
  2.   BQ25616, BQ25616J BMS026 Evaluation Module
  3.   Trademarks
  4. 1Introduction
    1. 1.1 EVM Features
    2. 1.2 I/O Descriptions
  5. 2Test Summary
    1. 2.1 Equipment
    2. 2.2 Equipment Setup
    3. 2.3 Test Procedure
      1. 2.3.1 Initial Settings
      2. 2.3.2 Charge Mode Verification
      3. 2.3.3 Boost Mode Verification
      4. 2.3.4 Helpful Tips
  6. 3PCB Layout Guideline
  7. 4Board Layout
  8. 5Schematic
  9. 6Bill of Materials
  10. 7Revision History

Equipment Setup

Use the following instructions to set up the equipment:

  1. Review EVM connections in Table 1-2.
  2. Set PS1 for 5-V DC, 3-A current limit and then turn off the supply.
  3. Connect the output of PS1 in series with a current meter to J1 (VAC and GND).
  4. Connect a voltage meter across TP7 (VBUS) and TP25 (PGND), or across J1.
  5. Turn on Load #1, set to constant voltage mode, and output to 3.7-V. Disable Load. Connect Load in series with a current meter (multimeter), ground side, to J5 (BATTERY and GND) as shown in Figure 2-1.
  6. Connect one voltage meter across TP15 (BAT) and TP24 (PGND), or across J4-2 and J4-1 as shown in Figure 2-1.
  7. Connect one voltage meter across TP14 (SYS) and TP24 (PGND), or across J2-1 and J2-2 as shown in Figure 2-1.
  8. Install shunts as shown in Table 1-3.
GUID-51911437-9408-4E79-8400-B08F8FC1CF32-low.gifFigure 2-1 Original Test Setup for BMS026 EVM