SLUUCW7 july   2023 TPS25983

 

  1.   1
  2.   Description
  3.   Features
  4.   Applications
  5.   5
  6. 1Evaluation Module Overview
    1. 1.1 Introduction
    2. 1.2 Kit Contents
    3. 1.3 Specification
    4. 1.4 Device Information
  7. 2Hardware
    1. 2.1 Test Points and Connectors
    2. 2.2 Test Equipment and Set Up
      1. 2.2.1 Power Supplies
      2. 2.2.2 Meters
      3. 2.2.3 Oscilloscope
      4. 2.2.4 Loads
    3. 2.3 Test Setup and Procedures
      1. 2.3.1 Hot-Plug Test
      2. 2.3.2 Current Limit Test
      3. 2.3.3 Output Hot-Short Test
      4. 2.3.4 Wakeup into Short Test
      5. 2.3.5 Overvoltage Cut-off Test
  8. 3Hardware Design Files
    1. 3.1 Schematic
    2. 3.2 PCB Layouts
    3. 3.3 Bill Of Materials (BOM)
  9. 4Additional Information
    1.     Trademarks

Wakeup into Short Test

Use the following instructions to perform wakeup into short test.

  1. Set the input supply voltage VIN to 12 V and current limit of 10 A. Turn OFF the power supply.
  2. Short the output of the device for example, VOUT to GND with a shorter cable.
  3. Turn ON the power supply.

Figure 3-5 shows test waveform of wakeup into output short on the TPS25983EVM eFuse Evaluation Board.

GUID-BAC63E44-FD1B-4F0D-BCBC-9834BFDDDFED-low.pngFigure 2-5 Test Waveform of Wakeup Into Output Short for TPS25983 Device