SNLA371B December   2020  – February 2024 DP83TG720R-Q1 , DP83TG720S-Q1

 

  1.   1
  2.   Abstract
  3.   Trademarks
  4. Introduction
  5. Hardware Configuration
    1. 2.1 Schematic
  6. Software Configuration
  7. Testing PMA
    1. 4.1 PMA Testing Procedure
  8. Testing IOP: Link-up and Link-down
    1. 5.1 IOP Testing Procedure
  9. Testing SQI
    1. 6.1 SQI Testing Procedure
    2. 6.2 Mapping SQI with Link Quality
  10. Testing TDR
    1. 7.1 TDR Testing Procedure
  11. Testing EMC/EMI
  12. 10Revision History

Abstract

OA TC12 mandates different tests for 1000BT1 PHY. This document describes the procedure to put DP83TG720R/S in the required test mode to carry out different TC12 tests.

The software and hardware configuration used during DP83TG720's TC12 testing can be found in this document. This configuration has been tested across different OA compliance houses: UNH, FTZ, and C&S and should be treated as a minimum requirement. Further improvement based on customer's system use-case is possible with additional hardware and software configuration.